Progress Claim Template: How to Write a Progress Claim in Australia

Dyllan Vosloo, Founder 24 October 2026 · 12 min read

A progress claim template sets out the work you've completed to date, what you've already claimed, any retention held back, the GST and the amount now due. A progress claim is a request for an interim payment on a job that isn't finished yet. In construction, the same document is usually your payment claim under your state's Security of Payment Act, which gives the other side a deadline of 10 or 15 business days to respond with a payment schedule. Copy the template below, then check the state table so the claim actually triggers those rights.

Need the invoice itself? The Australian invoice generator adds your ABN, 10% GST and a due date, and downloads a PDF in under a minute. For trade work, the tradie invoice template and contractor invoice template are set up for stage and labour lines.

What is a progress claim?

A progress claim is a written request for payment for the part of a contract you've completed so far. Instead of waiting until the end of a long job, you claim the value of work done at agreed points: monthly, at each stage, or at each milestone.

It's the same idea as "progress invoicing" in any industry. What makes construction different is the law behind it: every state and territory has Security of Payment legislation, and a claim that meets its requirements starts a statutory clock the client can't contract out of.

This page is about the claim document itself. For deposits, variations and the other invoices on a building job, see our guide to invoicing for building work.

What should a progress claim include?

A progress claim needs the standard invoice details plus a contract summary: the contract value, the work completed to date, the amount previously claimed and the amount claimed now. If you're registered for GST it must also meet the ATO's tax invoice rules, and in construction it should carry your state's Security of Payment wording.

The ATO's minimum tax invoice fields are covered in our tax invoice requirements guide.

Progress claim template you can copy

Copy this into your invoice, replace the bracketed placeholders and delete any line you don't need. The cumulative columns are what make it a progress claim rather than an ordinary invoice: anyone checking it can see the whole contract position on one page.

TAX INVOICE / PROGRESS CLAIM No. [3]

Invoice number: [INV-0412] · Date: [31 October 2026] · Due: [date per contract]

From: [Business name] · ABN [11 digits] · Licence [number] · [phone] · [email]

To: [Client name] · ABN [client ABN] · [billing address]

Project: [project name / site address] · Contract: [reference and date] · Work completed to: [date]

Contract sum (ex GST): $[ ] · Approved variations to date (ex GST): $[ ] · Revised contract sum: $[ ]

Item [1]: [description] · Value $[ ] · [%] complete · Value to date $[ ] · Previously claimed $[ ] · This claim $[ ]

Item [2]: [description] · Value $[ ] · [%] complete · Value to date $[ ] · Previously claimed $[ ] · This claim $[ ]

Variation [V1, approved date]: [description] · Value $[ ] · [%] complete · This claim $[ ]

Gross value of work this claim (ex GST): $[ ]

Less retention [5]% of this claim: −$[ ] · Retention held to date: $[ ]

Net amount this claim (ex GST): $[ ] · GST 10%: $[ ] · Total payable this claim: $[ ]

Paid to date: $[ ] · Balance of contract remaining after this claim (ex GST): $[ ]

"This is a payment claim made under the [name of Act and state]."

Payment: [account name] · BSB [ ] · Account [ ] · Reference [INV-0412]

Not a construction job? Drop the retention and Security of Payment lines and keep the cumulative columns.

What does the Security of Payment Act require in each state?

Each state and territory sets its own rules for what a payment claim must contain, how long the client has to dispute it with a payment schedule, and when payment falls due. Most require the claim to say it is made under the Act; Queensland and the Northern Territory don't. Get these wrong and your claim may not count as a payment claim at all.

StateActThe claim mustPayment schedule (response) dueWhen payment is due
NSWBuilding and Construction Industry Security of Payment Act 1999Identify the work, goods or services; state the amount; state that it is made under the Act. Head contractors attach a supporting statement. One claim per month per contractEarlier of the contract time or 10 business days after the claim is servedHead contractor: 15 business days. Subcontractor: 20 business days (or earlier if the contract says). Owner-occupier contracts: per the contract, or 10 business days if it's silent
VICBuilding and Construction Industry Security of Payment Act 2002Specify the work, goods or services and the amount; state that it is made under the ActEarlier of the contract time or 10 business daysThe contract date, which since 15 April 2026 can't be more than 20 business days after the claim; 10 business days if the contract is silent
QLDBuilding Industry Fairness (Security of Payment) Act 2017Identify the work or goods and services; state the amount; request payment. One claim per reference dateEarlier of the contract time or 15 business daysPer the contract, capped at 15 business days (commercial building contracts) or 25 business days (subcontracts); 10 business days if the contract is silent
WABuilding and Construction Industry (Security of Payment) Act 2021Be in writing (in the approved form, if any); state the amount; describe the items and quantities of work; state that it is made under the Act. An invoice can be a payment claimEarlier of the contract time or 15 business daysHead contractor: 20 business days. Subcontractor (or a principal with no head contractor): 25 business days, or earlier if the contract says
SABuilding and Construction Industry Security of Payment Act 2009Identify the work, goods or services; state the amount; state that it is made under the ActEarlier of the contract time or 15 business daysPer the contract; if it's silent, 15 business days after the claim
TASBuilding and Construction Industry Security of Payment Act 2009Be in writing and addressed to the respondent; state your name; identify the work in enough detail to assess; state the amount; state that it is made under the ActEarlier of the contract time or 10 business days (20 business days where the respondent owns the land, the claim is for a home and they aren't a building practitioner)Per the contract; if it's silent, by the end of the same 10 or 20 business day period
ACTBuilding and Construction Industry (Security of Payment) Act 2009Identify the work, goods or services; state the amount; state that it is made under the ActEarlier of the contract time or 10 business daysEarlier of 15 business days after the claim or the contract date
NTConstruction Contracts (Security of Payments) Act 2004Where the contract has no claims clause, the implied terms require a written claim addressed to the other party, with your name, the date, the amount and itemised workImplied terms: a notice of dispute within 10 working daysImplied terms: 20 working days. A contract term longer than 30 working days is read down to 30

Sources: NSW Government Security of Payment guide, Victorian Building and Plumbing Commission, QBCC, and the Acts on each state's legislation register, checked October 2026. Business days exclude weekends and public holidays, and some Acts also exclude a Christmas period. Some Acts exclude residential work for a home owner (WA, for example, excludes most home building contracts of $500,000 or less with an individual), so check yours before relying on the deadlines.

The safe habit: put the "made under the Act" sentence on every construction progress claim, even where it isn't required.

How do you write a progress claim? A worked example with retention and GST

Work out the value of everything completed to date, subtract what you've already claimed, deduct retention if the contract allows it, then add GST to the net amount. Here's how that looks for a Queensland subcontractor three months into a commercial fit-out.

The job: a joinery subcontract worth $200,000 plus GST, with 5% retention deducted from each claim. Claims 1 and 2 covered $80,000 of work. By 31 October 2026, the work is 65% complete and an approved variation for extra shelving (V2, $6,000) is fully installed.

LineValue (ex GST)% completeValue to datePreviously claimedThis claim
Contract works$200,000.0065%$130,000.00$80,000.00$50,000.00
Variation V2: extra shelving$6,000.00100%$6,000.00$0.00$6,000.00
Gross this claim$206,000.00$136,000.00$80,000.00$56,000.00

Then the bottom of the claim:

Check it the way the head contractor's quantity surveyor will: value to date ($136,000) minus retention held ($6,800) is $129,200, and earlier net claims ($76,000) plus this one ($53,200) also equal $129,200.

When is GST on retention payable?

If you account for GST on an accruals basis, the ATO's particular attribution rules for retention payments generally let you account for GST on the retained amount when you receive it or invoice it, not when you issue the progress claim. That's why the example charges GST on the $53,200 net claim, and you'd invoice the $6,800 retention plus GST when it's released after the defects period. Cash-basis businesses simply report GST when payment arrives. The rule sits in the GST retention payments determination; confirm the treatment with your tax agent if your contract handles retention differently, for example through a bank guarantee.

How often can you submit a progress claim?

As often as your contract allows, and under Security of Payment law, generally once per reference date. If the contract doesn't set a date, most Acts default to monthly claims. In NSW you can serve one payment claim per month under each contract; in Queensland the default reference date is the last day of the month the work was done.

There are outer limits too: NSW and Tasmania, for example, allow a claim within the contract's period or 12 months after the work was last done, whichever is later.

What happens after you send a progress claim?

The client either pays the full amount by the due date or sends a payment schedule within the deadline saying how much it will pay and why. If it does neither, most Acts make it liable for the full claimed amount, and you can recover it as a debt or apply for adjudication.

A payment schedule that pays less than you claimed opens the adjudication route, a fast decision on what's owed. The timeframes to apply are short, so diarise the response deadline the day you serve the claim. If the client goes quiet on an ordinary invoice instead, our guide to chasing overdue invoices covers the reminder sequence, and a letter of demand is the usual next step outside the Security of Payment process.

How does progress billing work outside construction?

Consultants, designers, developers and agencies use the same structure without the statutory overlay. You bill at agreed milestones or by percentage complete, show the running total, and add GST to each claim if you're registered.

Take a brand designer quoting $24,000 plus GST for a rebrand, billed 30% at discovery, 40% at concept approval and 30% at final files:

Milestone%Ex GSTGSTInvoice total
1. Discovery and strategy complete30%$7,200.00$720.00$7,920.00
2. Concepts approved40%$9,600.00$960.00$10,560.00
3. Final files delivered30%$7,200.00$720.00$7,920.00
Total100%$24,000.00$2,400.00$26,400.00

Define each milestone as something the client can see ("concepts approved in writing"), and put the schedule in the quote so it's agreed before you start; our guide to writing a quote shows where it goes.

On GST, the ATO's ruling GSTR 2000/35 treats each progressive component as a separate supply, so the GST on each milestone goes in the BAS for the period you issue that invoice or get paid for it, whichever comes first (or when paid, on a cash basis). You don't owe GST on the whole $24,000 up front.

Designers and engineers whose work feeds into a build may be covered by Security of Payment laws too, because the Acts extend to some services related to construction work. For more on billing professional work, see how to invoice as a consultant.

Five progress claims, five due dates. InvoiceSonic, our invoicing app, tracks which claims are overdue and sends automatic payment reminders at 7, 14 and 30 days after the due date, so a stage payment doesn't slip while you're on the next job.

What are the most common progress claim mistakes?

This article is general information, not legal or tax advice. Security of Payment laws change and their deadlines are strict, so check the current Act or your state regulator, see the ATO for GST, or speak to a construction lawyer or tax agent about your contract.

Frequently asked questions

What is the difference between a progress claim and an invoice?

A progress claim is an invoice for part of a contract, showing the contract value, work completed to date, amounts previously claimed and the amount due now. If you're registered for GST it should also meet the tax invoice rules, so one document can be both the progress claim and the tax invoice.

Does a progress claim need to say it is made under the Security of Payment Act?

In NSW, Victoria, WA, SA, Tasmania and the ACT, yes: the payment claim must state that it is made under the relevant Act. Queensland and the Northern Territory don't require the statement, but adding it does no harm.

How long does a client have to respond to a progress claim?

Under Security of Payment law the client must respond with a payment schedule by the earlier of the contract deadline or 10 business days in NSW, Victoria, Tasmania and the ACT, or 15 business days in Queensland, WA and SA. In the NT, where the implied terms apply, a notice of dispute is due within 10 working days.

Do you charge GST on retention in a progress claim?

On an accruals basis, the ATO's retention attribution rules generally let you account for GST on retained amounts when you receive or invoice them, so many contractors charge GST on the net claim and invoice the retention plus GST on release. On a cash basis you report GST when you're paid. Confirm the treatment for your contract with your tax agent.

Can consultants and designers use progress claims?

Yes. Any business can bill a project in stages by milestone or percentage complete. Each claim should show the running total, and GST applies to each claim separately if you're registered. Security of Payment laws only apply where the work is construction work or related goods and services.